Subject : Colônia drilling
Brazil, SP, Sao Paulo, Pareilheiros, Colônia crater (23.874°S - 46.705°W)
PI : Marie-Pierre Ledru, IRD, ISEM (Institut des Sciences de l’Evolution Montpellier), UMR 5554
CNRS staff for DT-INSU, C2FN : Laurent Augustin and Alain de Moya
For Colônia drilling, a support from C2FN-DT-INSU was required in 2017. But initial solicitation started in 2011 with providing an offer for a 50m drilling with a recovery core. In the mid time scientific project and drilling request did change several times. In 2014 the project became an ICDP project and a workshop was financed to evaluate the feasibility of 2 drilling 450m and 500m depth in order to reach bed rock and collect sample indicated meteorite impact traces possible origin of the crater. Simultaneously to the workshop, a one day hand drilling reached 15m with a recovery core with C2FN support.
In 2016, with ICDP refusal, PI decided to switch to the original project and got a LEFE and a BNP Paribas grant and an official support from DT-INSU for a 50m drilling and its recovery core.
Two kinds of support :
Drilling operation started end of July beginning of August. After a reconnaissance penetration test, performed beginning of July, SONDOSOLO, the subcontractor, decided to drill with a hammering and pushing corer with tubing.
SONDOSOLO arrived on site with one day of delay and an equipment not similar to the one described on the offer. After the tests performed beginning of July, we decided to be confident and to leave the company to drive his task as they indented with the equipment brought: A tripod with hand hammering system. Without any handling means, all equipment was carried by hand to the site and one day was necessary to set up all the equipment.
Immediately it appeared that the tripod was not high enough to handle 3m rods. After 2 days, a first drilling abort at 3m and a few modification on the drill, the second drilling was interrupt at 13.5m for lack of penetration.
By Friday 4/08 at 14:00, we intimate the company to bring, on site, by the days after at 8:00, a drilling equipment similar to the one described on the offer, if not contract will be break off…
The day after a new equipment was on site with the promise of a new drilling team for Monday 07/08.
Drilling operation restated really on Monday after mid-day. All Saturday was needed for drilling pad setting up. Tuesday evening, 30m depth was reached and a 51m core completed by Thursday noon with some difficulties.
Drill rig was moved by a few meters to start the duplicate core at the first time on Friday. 30.80m depth was reached Friday evening and 45.80m by Saturday evening. On Monday by mid-afternoon, duplicate core was achieved at 50.30m under PI supervision. C2FN staff was already in the retrograde plane on Sunday 13/08 as initially planed.
Initial goal is reached with a 51m core and a 50.30m duplicate core completed with a recovery rate over 95%. This give a 50m long sediment continuous sequence.